Saccarappa Construction Updates

The following page will give periodic updates and share milestones in the construction and renovation of Saccarappa School

December 9, 2017

The Above video is from December 9, 2017 taken after the Breakfast with Frosty celebration and before the Saturday snow.  As you can see the steel has been erected for a couple of sections and site work continues.  Our students have very much enjoyed watching the steel workers as well as the big crane that has put the steel into place.  

 

November 27, 2017

The video below marked November 23, 2017 shows progress to date.  This may be the last video before the actual building is constructed.  Steel was delivered to the site earlier in the week and as of November 27 is beginning to be erected.  The next video should show the shape of the school building and give the viewer a sense of what Saccarappa will look like in the future.  In the video, you can see the complete "foot print" of the school.  The courtyards especially the one nearest the first phase of construction can also be seen clearly.

October 31, 2017

We had not school on October 30 due to the big wind storm that came through the northeast on Sunday into Monday.  Thankfully, the storm did minimal damage to our school or the construction site.  Other than some construction fences and saw horses being knocked down, the school weathered the storm without incident.  Steel is scheduled to arrive sometime during the month of November and then we should see a great many external changes.  Stay tuned!

October 15, 2017

Over the weekend, lines were painted on the pavement so that parking spots and driving patterns are well established.  The bus loop has one way traffic in two lanes and the road leaving the school parking lot has two lanes of traffic.  Construction has also started on the footers nearest the bus loop.  The general contractor, Arthur Dudley, appears to have the project on schedule and progressing at a very quick pace. 

October 10, 2017

Over the Columbus Day weekend, Shaw Brothers completed the grading and first coat of paving of the parking lot and bus loop.  The paving in concert with the beautiful wooden fencing around the retaining pond has created the beginnings of a finished look to the parking lot.  More importantly, it has also made the bus loop safer for children and their teachers.  As you can see from the photos and video, the footings are nearly completed for the new classroom wing.

September 13, 2017

As we settle into the school year, our wonderful Saccarappa family is getting used to the "new normal" of being a construction site.  The first 100 yards of wood chips have been delivered and spread over a muddy part of our playground.  On Saturday September 8, 2017 a group of individuals from the school department and one generous Saccarappa family volunteered their Saturday morning to clear the play area of remaining roots and debris.  On Tuesday September 12, 2017 a second 100 yards of wood chips were delivered.  The wood chip "mountain" is waiting to be spread sometime later this week.  

Our construction project is still well ahead of schedule.  Currently the construction crew continues to prepare the ground and pour the footings for the foundation of the Saccarappa addition.  

August 31, 2017

Construction has continued to proceed at a surprising rate.  Much of the parking area and bus loop is approaching readiness for paving and the builders have already begun to dig the foundation for the new wing of the school.  More importantly, school has opened and while everything was not perfect, we had a very smooth start that was good for children.  The addition of a crossing guard has been most helpful.  

There were two news stories about the project.  One was on the front page of the Portland Press Herald called Westbrook Students Returning... and another television interview on Channel 6 called Schools Under Construction.  Both are an accurate picture of how the projects are going and their impact on school.

August 14, 2017

We are in week two of construction and things are still moving rapidly at Saccarappa School.  The ground where the building, parking lot and baseball/softball field will be build has been cleared, graded and they are in the process of installing drainage features.  As you can see from the photos, the back of the school looks nothing like it did at the end of July.  Although it is difficult to see, there is a fairly substantial grass area with a path leading out to it from the back side of the building.  This will be fenced, made safe and will become our play area for recess for the next two school years.

 
 
Dr. Lancia Signing Contract with Arthur C. Dudley

Dr. Lancia Signing Contract with Arthur C. Dudley

July 27

Meetings were held at the Westbrook City Hall and at the Westbrook School Department with school and city officials as well as representatives from Harriman Associates (the project architect and engineering firm) and Arthur C. Dudley (the contractor for both the WMS and Saccarappa project) to finalize contracts and open a dialogue between all involved parties associated with this project.


Links to Construction Video History

November 23 Video

October 7 Video

Aerial Panoramic Photo October 7, 2017

Aerial Panoramic Photo October 7, 2017

Video of Saccarappa Construction Taken on October 7, 2017

Before and After Photos

Below is a series of images taken from about the same place on three different dates.  As you can see, our friends at Shaw Brothers have been busy preparing the school grounds for the start of construction.  
 
 

Another Set of Perspectives